What are the faults of the boom system of the concrete pump truck?
Concrete pump truck is a commonly used equipment in engineering construction.Its main function is to transport concrete for construction projects.However,during the early work of our pump truck,various problems and failures will occur,which makes our staff hard to guard against.What are the common failures?
1.The pipeline is blocked.The blockage of the pipeline of the concrete pump truck is a common fault when the boom pump frame system is working.
There are two general manifestations of pipeline blockage.If the amount of concrete transported exceeds the range of the pump truck itself,it will generate a lot of pressure during the pumping process of the pump truck,which will cause the pumping behavior to not be carried out normally and the pipeline will be blocked.
(2)The boom runs slowly.When the boom of the concrete pump truck runs slowly,there will be some abnormal phenomena,such as the controller cannot accurately control the boom,and the boom operating device is stuck.If the above problems occur when the boom of the concrete pump truck is running,it means that the boom is running slowly.
(3)Arm drop phenomenon.The failures in the boom system of the concrete pump truck also include the failure of the boom.When the concrete pump truck is affected by the transmission pressure,it will cause the boom to slide down.The range of the boom is limited.If it exceeds the permitted range of slide down,it means that the concrete pump truck has dropped the arm.Based on experience,the main reason for the drop arm situation is due to leakage.When the arm drop occurs,the concrete pump truck should be driven to a safe area and the cause of the arm drop should be checked.